SUPREME COURT INTERPRETATION · № ას-459-438-2015

Lost profits in a real-estate pre-contract

When may lost profits be claimed after a commercial property deal fails?

OVERVIEW

Why this decision matters

Property buyers and developers should document agreed specifications, change control and credible evidence of projected income. The ruling is not an automatic guarantee of lost profits.

01

Facts and procedural context

The buyer alleged that important access and common-area features of a planned retail unit were changed, undermining its intended use. Claims included refund of the price, contractual penalties, financing costs and projected income.

02

Core judicial reasoning

The analysis turns on the distinction between contract breach and proof of the asserted future financial benefit, including causation and reliable supporting evidence. Different instances assessed the claims differently.

03

Practical implications

Property buyers and developers should document agreed specifications, change control and credible evidence of projected income. The ruling is not an automatic guarantee of lost profits.

SOURCE AND VERIFICATION

Read the complete court interpretation

This independent editorial analysis does not replace the decision. Confirm the legislation applicable at the time and the current version.

Full interpretation (PDF)
THE NEXT STEP

Need an assessment of your case?

Share the key facts and intended outcome. We can identify the initial scope and next steps.

Start a conversation